Pilot Tube Micro Tunnelling Method (PTMT)

Pilot Tube Micro Tunnelling

Pilot Tube Micro Tunnelling Method is designed to be compact and simple for small pipe installation. It is ideal for location with limited working space. It also has the following advantages:

  • Short setup time
  • Can operate in area of high water table
  • Minimum disruption to existing services
  • Small “on the ground” site requirement
  • Small jacking / receiving pit

Method to install pipe consists of the following :

  • 1st Stage: Steerable pilot tube is jacked into the ground displacing the soil.
  • 2nd Stage : Temporary casing with auger is installed
  • 3rd Stage : Product pipe is installed

Our Photos

ptmt_3

2m to 3.6m diameter jacking/receiving pit using precast concrete shaft

ptmt_4

Above ground set up – safety railing & power pack

ptmt_1

Jacking temporary casing with auger inside jacking shaft

ptmt_2

Jacking product pipe inside jacking shaft

PILOT TUBE MICRO TUNNELLING METHOD

Ideal for location with limited working space. PTMT is designed to be compact and simple for small pipe installation.